At the bottom of Secline Street, Kings Beach's smaller beach is still mostly what it has been for years. NTPUD's environmental study describes it as a small, quiet, undeveloped local beach. There are a few picnic tables, portable toilets and paddleboard and kayak racks run by a rental concessionaire. There are no ADA-accessible restrooms and no ADA-accessible way onto the sand. Kings Beach State Recreation Area, a few minutes away, has 979 feet of frontage, a playground, restrooms and its own parking. Secline sits on a much smaller footprint, and its design was always going to be a different problem.
On November 3, 2026, the North Tahoe Public Utility District board adopted Resolution 2026-22. That resolution approved the environmental findings for the Secline Beach Enhancement Project and approved the project itself, on the condition that it follows the required mitigation measures. A beach this size usually gets a new restroom only after years of grant applications. This one has moved faster because of an accident that happened several miles west.
The restrooms trace back to Carnelian Bay
On July 18, 2024, a subcontractor working on a Caltrans Highway 28 project in Carnelian Bay punctured a sewer force main owned by NTPUD. That pipe is the main line carrying raw sewage out of the Lake Tahoe area. The Sierra Sun reported that on August 13, 2025, the Lahontan Regional Water Quality Control Board finalized an $850,000 settlement with Caltrans and NTPUD. Of that, $5,000 is set to go to a state cleanup account. The other $845,000 is set to go to the NTPUD-led Secline Beach Supplemental Environmental Project, which the paper described this way:
"The project will construct permanent public restrooms to replace the portable toilets currently at Secline Beach. Trash receptacles, public drinking fountains and improved stormwater control will also the improve facilities there."
The settlement also sets a deadline. According to the Sierra Sun, the agreement requires the project to be completed within 48 months, and in September 2025 construction was expected during the 2028 season. That deadline explains why a beach left undeveloped for decades now has a plan and a timeline.
The settlement is one of several funding sources. The district's FY 2026/27 Recreation Fund capital budget includes $397,660 for the project. A $90,000 California Tahoe Conservancy grant paid for the environmental work, and NTPUD did not have to match it. NTPUD also received a $240,000 multi-year North Tahoe Community Alliance TOT-TBID grant for planning and design.
Three owners, one small beach
The money is in place, so the design question is mostly about land. Secline is three public parcels side by side. NTPUD owns the eastern shoreline, the California Tahoe Conservancy owns the central parcel, and Placer County owns the western parcel along Griff Creek. NTPUD does not own all three, so it drew two versions of the plan.
| Concept A | Concept B | |
|---|---|---|
| Restroom location | Conservancy's central parcel | NTPUD's eastern parcel |
| Restroom type | Multi-occupant, ADA-compliant men's and women's facility with an outdoor pedestal shower | Same type of permanent restroom and adjacent shower |
| Paddleboard and kayak racks | 60 standard plus 14 accessible | 74 standard plus 14 accessible |
| Effect on the sand | Keeps beach space on NTPUD's parcel and avoids pushing further into the backshore | Only minor improvements on the Conservancy parcel |
| Requires a land exchange | Yes | No |
The environmental documents say the main differences between the two concepts are the restroom's location and where the bike racks go. In Concept A, the building goes on the central parcel and the eastern shoreline stays open for beachgoers.
A forest off Stewart Way decides where the restroom goes
Concept A needs a land swap, and the land NTPUD would give up is nowhere near the water. The district owns about 10.2 acres of undeveloped forest at the north end of Stewart Way, roughly 300 feet north of State Route 267. The planning documents describe it as level to gently sloping, with a forest setting and mountain views. In the exchange, the Conservancy would take that parcel and NTPUD would receive the Conservancy's roughly 0.29-acre Secline shoreline parcel.
For neighbors of the Stewart Way parcel, the documents say the land would stay as it is now, with no change in use or maintenance. The Conservancy would manage it for recreation, habitat and open space. The exchange still needs separate approval from both the Conservancy board and the NTPUD board. Any formal action was expected after the environmental review and the NTPUD board's vote on the project, and that vote happened on November 3. Concept B is the version that gets built if the swap is not approved.
What changes no matter which concept is built
Both versions add the same set of improvements, and most of them help people who arrive by bike, on foot or carrying a board:
- A 10-foot shared-use path with a pedestrian bridge over Griff Creek
- A concrete watercraft loading zone and stepped beach access using natural boulders
- A removable ADA beach access mat, plus an accessible picnic table and an accessible rack
- Movable picnic tables and an outdoor classroom on the east side of Griff Creek
- 10 bicycle racks holding up to 20 bikes
- Eight bear-proof trash receptacles in place of the existing dumpster
- A replacement screening fence and vegetation thinning
The final environmental document says the stated goal is to add amenities, access and walking and biking routes while keeping the beach's existing character. It also confirms that the permanent restrooms will include waste disposal and drinking water. One change came out of consultation with the Washoe Tribe. In the final version, the trail routes were moved to avoid a recorded bedrock mortar feature. In practice, the path runs where it does partly to protect a cultural site that predates the beach as people know it today.
What stays the same at the curb
Neither concept changes vehicle parking or traffic circulation. Most of the street-level work was already finished in 2023. Placer County's Lower Secline water-quality project paved the old dirt roads, stabilized the shoulders, added sidewalks and formalized beach parking. The new work happens on the sand and along the creek. Getting a car to Secline should work the way it does now.
What has to happen before construction
The board packet for the November 3 vote says the resolution does not authorize construction contracts or spending beyond money already budgeted, and the project still depends on permits, including any TRPA approvals. The steps are listed in the district's November 3 board packet and the September 2026 environmental study:
- A TRPA Recreation Permit and a Lahontan NPDES permit
- A streambed alteration agreement with the California Department of Fish and Wildlife for the work at Griff Creek
- Right-of-way approvals from local agencies and Caltrans, plus NTPUD water and sewer connections
- Section 404 and 401 water permits, if protected aquatic resources are affected
- Separate board approval for any construction contract or additional funding
- For Concept A only, approval of the land exchange by both agency boards
When work does start, it will be phased over several years. The environmental study describes temporary access restrictions only in active work areas and on the trail segment, in early or late summer. It says parts of the beach outside those areas will stay as open as they are now. Peak July days at Secline are not expected to be lost to construction.
This winter, the action is in the town core
Nothing changes on the sand at Secline this winter. On Friday, December 4, the district's Holiday Tree Lighting and Photos with Santa runs from 5 to 7 p.m. at the North Tahoe Event Center, 8318 North Lake Boulevard. Entry is free. There will be music from the Truckee Tahoe Community Choir and the North Tahoe Jazz Band, crafts from the Boys & Girls Club of North Lake Tahoe, and free books from Friends of the Library. Santa photos cost $10 for residents and $20 for non-residents, and the district says they sell out, so book a time slot in advance.
The Merry & Bright Holiday Stroll overlaps with the tree lighting from 6 to 8 p.m. that night, and more than 20 local businesses are scheduled to stay open late. It runs again on Saturday, December 12, from 5 to 8 p.m. That night, Tahoe Sleigh & Carriage Rides offers free carriage rides from 5:30 to 7:30 p.m., leaving from the Kings Beach Visitor Information Center and the North Tahoe Event Center. On both nights, the Visitor Information Center offers free gift wrapping for local purchases over $25 if you show your receipt. For more of what the town offers in summer, see our guide to outdoor activities in Kings Beach.
At Mountain Luxury Properties, we follow public projects like Secline from the first board vote through the final permit, because a new restroom, a creek bridge or a land swap can change how the streets around a beach work. If you own near Secline Street or Stewart Way and want to talk about what this plan could mean for your property, Book a Private Consultation.